HALO MANCHESTER

Build Update 25th May 2018

May Updates:

The metal framework for all floors is now complete.

The sixth floor is now built and the building is now watertight.

Internal plasterboard walls are now in excess of 50% complete.

Windows and external brickwork are currently at 65%.

First fix Mechanical and Electrical works are being carried out on four floors

Build Update 13th April 2018

Estimated Completion Date: 12th October 2018

5th storey floor steel frame in place, concrete shortly to be poured

Final 6th floor to be constructed shortly

Build Update 9th March 2018

Building Completion: 


External Scaffold is 80% complete

Metal frame and flooring to 3rd floor is complete

Metal frame and flooring to 4th floor is 35% complete

Window installation is 30% complete

Face brickwork is 15% complete

IOnsulation to the ground floor soffit is complete

Basement lighting and ventilation is 20% complete

Underslung soil and rainwater pipes is basement is 10% complete

Fix containment in corridors is 15% complete

Mechanical 1st fix is 5% complete

A welfare facility has been formed in the basement to allow space for the hoist to be fitted

Delays:

On site works have been further delayed by the inclement weather in the month - 16 hours of high winds, 30 hours of rain and 14 hours of frost

Weather:

Rain in the mont : 30 Hours

Rain since commencement : 190 Hours

High wind in the month : 22 Hours

High wind since commencement : 73 Hours

Frost in the month : 14 Hours

Frost since commencement : 31 Hours